Use baseline to get the difference between plan and actual
Gantt chart should update to the latest schedule as the project progress. But, you will want to keep the initial plan approved by the stakeholders to get the difference between the plan and the actual.
You can achieve it with the baseline feature.
How to use baseline
Set baseline when you have finished the initial plan
Open Gantt chart editor
Open the
Features
menu dropdown and selectShow baseline
Click the refresh baselines menu
Save the Gantt chart
Get the difference between plan and actual
Check the show baselines under the feature menu to display baselines
Hovering cursor onto baselines shows insights if the latest schedule is behind the baseline or takes longer than baseline