This feature is not available for Jira Work Management projects due to Jira specification limitations.
WBS Gantt-Chart for Jira Cloud does not have a direct Gantt chart view of projects like WBS Gantt-Chart for Jira Data Center/Server.
But it is possible to display a Gantt chart within the project screen by linking the created Gantt to the project, like a Scrum/Kanban board.
Access Gantt from the project sidebar
You can access the Gantt linked to the project by clicking on the "WBS Gantt-Chart" menu on the project sidebar.
If the project manager has not yet linked the Gantt to the project, the following screen will appear
If you have project management privileges, you can access the project configuration screen via the "Configuration" button to set up the project and gantt links.
Linking the project to a Gantt
To link a project to Gantt, access the following page from the project settings screen
Project settings > Apps > WBS Gantt-Chart
From "Select a Gantt," select the Gantt you wish to link to the project.
If you do not use Gantt in your project and wish to hide the menu in the project sidebar, check the "Hide sidebar icon" checkbox.
Additional Help
If you have any questions please feel free to ask a member of the Atlassian community!
Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.