Gantt calendar settings
What is the holiday calendar?
Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.
Holiday calendar example
This is an example of the holiday calendar, showing two scenarios, A and B, as follows:
Conditions:
Scenario A
Value | |
---|---|
1st regular holiday | - |
2nd regular holiday | - |
Holidays | - |
Scenario B
Value | |
---|---|
1st regular holiday | Saturday |
2nd regular holiday | Sunday |
Holidays |
|
Note: is Monday.
Issue values
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Operations
Drag-and-drop the Gantt bar so the issue starts on .
Results
Scenario A
This scenario does not have holidays, so the issue values are as follows:
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Scenario B
In this scenario, , , and will not be counted since they are defined as holidays.
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Confirm holiday calendar settings
Click Calendars on the Gantt configuration screen.
Holiday calendar items
Use Share Calendar
When enabled, use the global shared calendar.
Regular holiday
Check the non-working days in the week
Week Numbers
This item sets the week number and the starting day of the week.
If US is selected, the week in the Gantt chart is displayed starting on Sunday, and the week number is also displayed in US style.
If ISO-8601 is selected, the week in the Gantt chart is displayed starting on Monday, and the week number is also displayed in the ISO-8601 style.
Year
Filter to show the holiday in the years from Holiday List
Holiday List
This is a list of the dates you have registered as holidays.
Import Holidays
Choose Year and Country to import the public holidays from Google Calendar
Additional Help
If you have any questions please feel free to ask a member of the Atlassian community!
Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.