Input task results
Entering progress rate (percent done)
Where the task has progressed as a result of work done, you should input the data accordingly.
Entering progress rate
The data you need to input changes depending on the progress settings. Speak to the project manager for more details.
Managing progress rate in custom fields
If you are managing the progress rate in a custom field, enter the progress rate directly in the progress rate column of WBS Gantt-Chart.
Automatic calculation from time tracking
If you are using the automatic calculation from time tracking function, you cannot enter data directly from WBS Gantt-Chart. Follow these steps to enter time spent and the estimate of time remaining:
Click on the issue name
Edit items related to time tracking
More information
For more details, take a look at the Jira documentation on editing issues.
Automatic calculation from specified field
To calculate automatically from a specified field, enter the values in the specified field.
Updating issue status
If you start or complete a new issue, update the status of the issue.
This will resolve the warning icons and .
Click on the issue name
Edit all the status-related items
More information
For more details, take a look at the Jira documentation on editing issues.
To update warning icons, just reload WBS Gantt-Chart.
Additional Help
If you have any questions please feel free to ask a member of the Atlassian community!
Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.