What is the holiday calendar?
In WBS Gantt-Chart:
Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.
Holiday calendar example
This is an example of the holiday calendar, showing two scenarios, A and B, as follows:
Conditions:
Scenario A
| Yes / No |
---|
Regular holidays | - |
---|
Holidays | No |
---|
Scenario B
| Yes / No |
---|
Regular holidays | Saturday, Sunday |
---|
Holidays | |
---|
Note: is Monday.
Issue values
| Value |
---|
Start date | |
---|
Finish date | |
---|
Duration | 2 days |
---|
Operations
Drag-and-drop the Gantt bar so the issue starts on .
Results
Scenario A
This scenario does not have holidays, so the issue values are as follows:
| Value |
---|
Start date | |
---|
Finish date | |
---|
Duration | 2 days |
---|
Scenario B
In this scenario, , , and will not be counted since they are defined as holidays.
| Value |
---|
Start date | |
---|
Finish date | |
---|
Duration | 2 days |
---|
Confirm holiday calendar settings
Click Calendars on the left-hand side of the Gantt configuration screen.
Holiday calendar items
Regular holidays
Check the box for the day of the week to be a fixed holiday.
Holidays
This is a list of the dates you have registered as holidays.
Update holiday calendar
Click Edit on the upper right-hand side of the holiday calendar configuration screen.
Check the box for Regular holidays.
Enter specific holidays using YYYY-MM-DD format. Enter one date per line.
Click Update.
Additional Help
If you have any questions please feel free to ask a member of the Atlassian community!
Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.
Ask the community