How to disable the Create Story and Create Epic options on a Project?
Question
How can I disable the Create Story and Create Epic options that were enabled after installing WBS Gantt-Chart?
Answer
To disable the options Create Story and Create Epic for a Project, the related steps are described below, please follow them accordingly:
In the Project screen, go to Project settings, located in the left bottom of the screen
![](../__attachments/4212228987/project%20settings.png?inst-v=0ecc21a2-c016-4437-8af7-c167b768abda)
At the Project settings screen, select the WBS Gantt-Chart option located at the bottom of the list
![](../__attachments/4212228987/wgc%20option.png?inst-v=0ecc21a2-c016-4437-8af7-c167b768abda)
On the Create child issue section, click on the Edit button
![](../__attachments/4212228987/child%20issue.png?inst-v=0ecc21a2-c016-4437-8af7-c167b768abda)
On the Create child issue message box, uncheck the box Top of operations toolbar
![](../__attachments/4212228987/top%20toolbar.png?inst-v=0ecc21a2-c016-4437-8af7-c167b768abda)
Click on the Update button to save your changes.