Exporting to Microsoft Project
Exporting to Microsoft Project
You can export projects, versions and issues displayed in WBS Gantt-Chart as XML files that are readable in Microsoft Project by clicking Data ⇒ MS Project export on the operations bar.
This feature supports exporting hierarchies and dependencies (including lags), as well as several fields.
The correspondence table between the Jira and Microsoft Project fields is provided below.
WBS Gantt-Chart for Jira (Jira field) | Microsoft Project field | Notes |
---|---|---|
Summary | Task name | |
Assignee | Resource name |
|
Units | ||
Start date | Start date | Uses the value of the field configured as "Start date” in WBS Gantt-Chart for Jira |
Finish date | Finish date | Uses the value of the field configured as "Finish date" in WBS Gantt-Chart for Jira |
Baseline start date | Standard start date | Uses the value of the field configured as "Baseline start date" in WBS Gantt-Chart for Jira |
Baseline finish date | Standard finish date | Uses the value of the field configured as "Baseline finish date" in WBS Gantt-Chart for Jira |
% done | % complete | Uses the value of the field configured as "% done" in WBS Gantt-Chart for Jira However, in Microsoft Project, the % completion rate of a summary task is automatically calculated including accumulated % completion of child tasks as well. Therefore the value shown may differ from % done in WBS Gantt-Chart for Jira. |
Due date | Deadline |