You can check for issue dependencies by looking at the blue arrows displayed between the Gantt bars. If there is a blue arrow from a predecessor issue pointing towards a successor issue, this indicates that the successor issue depends on the predecessor issue.
Types of task links or dependencies
There are four types of task links as follows:
Type
Dependency
Start-to-Start
A successor task cannot start until its predecessor task starts.
Start-to-Finish
A successor task cannot finish until its predecessor task starts.
Finish-to-Start
A successor task cannot start until its predecessor task finishes.
Finish-to-Finish
A successor task cannot finish until its predecessor task finishes.