Configuring the hierarchy, dependency, and scheduling

In WBS Gantt-Chart for Jira, you can use Jira issue links to maintain the hierarchical relationships and dependencies of issues, and use Jira issues to maintain various data such as start and finish dates.

  1. Jira Setting ⇒ Apps 

  2. Select Issue in WBS Gantt-Chart

  3. Set the issue link type and Jira fields to be used in WBS Gantt-Chart for Jira.

  4. Click Update