Editing the progress rate 

On the issue configuration screen, select Percent Done. You can select from four configurations as follows:

Use specific field

The percent done is based on WBS Gantt-Chart data. You can edit these values in WBS Gantt-Chart.

Calculate with time tracking automatically

Automatically calculates progress rate based on the "time spent" and the "time remaining estimate." The equation is as follows:

Time Spent / (Time Spent + Time Remaining Estimate) * 100
CODE

You cannot edit the progress rate in WBS and Gantt chart when you choose this setting.

Setting the creation date in the schedule when creating an issue or version

When you create a version or issue from a project or version, you specify whether to set the creation date as the planned date.

Editing dependency links

You can enable only specific dependencies among Start-Start, Start-Finish, Finish-Start, and Finish-Finish dependencies.

To change the start month of a fiscal year

If the display units in WBS Gantt-Chart are set to quarters, these will be shown on a fiscal year basis.
For example, if the start month of the fiscal year is March, the first quarter (Q1) is March to May.

You can change the start month of the fiscal year as follows.

  1. Select the chosen month as the start month of the fiscal year.

  2. Click Update.

Additional Help

If you have any questions please feel free to ask a member of the Atlassian community!

Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.

Ask the community