Gantt Chart Planner for Confluence Cloud

Change Gantt chart size in view mode

Change Gantt chart width

  1. Edit the page the Gantt chart is on

  2. Click the Gantt chart

  3. Change width

chnage  width.gif


Change Gantt chart height

  1. Open Gantt chart editor

  2. Open the configuration panel

  3. Change height values

  4. Close the configuration panel by clicking the update button

  5. Save the Gantt chart

gantt height.png